Purpose
Acceptance, execution and delivery of Work Packages.
Acceptance, execution and delivery of Work Packages.
Corp. Or Prog. Mgmt: |
||||
Executive: |
Approves creation of specialist Products. |
|||
Senior User: |
Approves creation of specialist Products. |
|||
Senior Supplier: |
Approves creation of specialist Products. |
|||
Project Manager: |
Creates Work Package; approves Team Plan; reviews Issues and Risks; reviews Quality Reports and Change Requests. |
|||
Team Manager: |
Creates specialist Products, Configuration Item Records, Team Plan, Change Request; raises Issues and Risks; reviews Quality Reports; updates Work Package; obtains approval Records |
|||
Project Assurance: |
Reviews WP, Team Plans, approval Records |
|||
Project Support: |
Updates Quality Register, Configuration Item Records; reviews approval Records. |
Business Case (Why): |
Business Case is reviewed in case of new Risks and changes in Benefits. |
|||
Organisation (Who): |
Reporting requirements from Communication Management Strategy. |
|||
Quality (What): |
Review Quality Register and approval Records. |
|||
Plans (How, How much, When): |
Team Plan is created. |
|||
Risk (What if): |
Escalate new risk information. |
|||
Change (What is the impact): |
Escalate Issues to Project Manager. |
|||
Progress (Where are we, direction, should we carry on): |
Review Work Package, create Checkpoint Reports, update Team Plan to show WP is complete. |